2016 Report details for project: ABUJA New Office and Residence
Project name | ABUJA New Office and Residence - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | FCO (D13) - see all reports for this organisation |
Report year | 2016 (data is from September 2015) |
Category | Infrastructure - see all reports for this category |
Description: | To provide a secure modern fit for purpose HMG office compound for both BHC and DFID in Abuja, Nigeria. |
DCA (RAG) | Amber |
DCA text: | Amber is appropriate at this stage in the project given the challenges with achieving the required quality of workmanship in Nigeria using local labour. Additional exPat supervision and UK supplier input has been procured to support the main contractor with the remainder of the works and completion of the construction works is now set for June 2016 with occupation by the end of 2016. |
Start date | 2011-01-01 |
End date | 2016-12-01 |
Schedule text | Data not provided |
Baseline | £18.80m |
Forecast | £18.80m |
Variance | None% |
Variance text: | Budget variance less than 5%. |
Whole Life Cost | £46.00m |
WLCost text: | Whole life costs remain as reported in the last annual report and in line with budget approvals. |
Notes1: | Budget variance less than 5%. |
Notes2: | |
Sourcefile | IPA_2016.csv |