2015 Report details for project: Defence Information Infrastructure
| Project name | Defence Information Infrastructure - there are 3 reports for this project: 2013, 2014, 2015 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | MOD (D17) - see all reports for this organisation |
| Report year | 2015 (data is from September 2014) |
| Category | ICT - see all reports for this category |
| Description: | To deliver to Defence a secure and coherent information infrastructure at best value for money and to approved cost. Due to its size and scope, DII is being delivered incrementally, delivering capability across the following areas: Increments 1, 2a & 3a: Fixed (SECRET & below). Increment 2b: Deployed (SECRET); DII Maritime is being delivered as part of Increments 1 and 2b. |
| DCA (RAG) | Amber/Red |
| DCA text: | The MPA RAG rating at 2014/15 Q2 acknowledged that the totality of the programme could not be delivered within its approved timeline. Plans were put into effect to assess the capability that would need to be transferred into successor programmes and approval sought to enact this. DII will end as a programme in March 2015, with GRAPEVINE1 providing successor services and supporting the delivery of the DII capability identified as outstanding beyond March 2015. A high level of activity is required of DII, however, before programme closure on 31 March 2015. |
| Start date | 2001-09-03 |
| End date | 2015-03-21 |
| Schedule text | Schedule being accelerated to achieve maximum benefits available. |
| Baseline | £770.20m |
| Forecast | £787.39m |
| Variance | 2.20% |
| Variance text: | Budget variance less than 5% |
| Whole Life Cost | £7,432.41m |
| WLCost text: | DII's cost of ownership within programmed approvals. |
| Notes1: | |
| Notes2: | |
| Sourcefile | IPA_2015.csv |