2015 Report details for project: Smart Metering Implementation Programme

Project name Smart Metering Implementation Programme - there are 11 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation DECC (D11) - see all reports for this organisation
Report year 2015 (data is from September 2014)
Category Infrastructure - see all reports for this category
Description: The Government's vision is for every home in Great Britain to have smart electricity and gas meters by 2020. Smart Meters will give consumers up-to-date information about how much gas and/or electricity they have used in pounds and pence, as well as units of energy. Smart meters will have benefits for consumers, suppliers and energy networks. Consumers will have near real-time information about their energy use, enabling them to monitor and manage their energy consumption, save money and reduce carbon emissions. Switching between suppliers will also be made simpler. Energy suppliers will have access to accurate data for billing and will be able to offer a wider range of services and tariffs. Energy networks will have better information to manage and plan current activities and support the move towards the development of a smart grid.
DCA (RAG) Amber
DCA text: A MPA Gate 0 Review in June 2014 reflected the good progress made since the last Gate Review in 2013, but acknowledged that there remained a number of areas requiring close management attention by the DECC programme team. The Programme needs to continue to work closely with multiple cross-industry delivery partners to ensure Programme success. There is limited contingency in the plan up until live operations of the Data and Communications Company and the critical path activities remain demanding.
Start date 2009-12-02
End date 2020-12-31
Schedule text On schedule for 2020. (The Data and Communications Company issued a consultation in Q4 2014 on revised plans for delivery of its initial operational services.)
Baseline £11.38m
Forecast £13.14m
Variance 15.40%
Variance text: The 2014/15 forecast is £13.14M which includes an increase of £1.76M to fund additional assurance and risk reduction activities in line with recommendations from the National Audit Office and MPA Review.
Whole Life Cost £19,258.00m
WLCost text: Whole Life Costs are presented in nominal terms for comparability with other programmes. Previous figures were expressed in 2011 real prices, for consistency with the published Smart Meter Programme Impact Assessment. Changes in the provided numbers are solely driven by the change in methodology, not by underlying cost changes.
Notes1: Smart Meters Implementation Programme
Notes2:
Sourcefile IPA_2015.csv