2014 Report details for project: JAKARTA: New Embassy

Project name JAKARTA: New Embassy - there are 2 reports for this project: 2013, 2014
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation FCO (D13) - see all reports for this organisation
Report year 2014 (data is from September 2013)
Category Infrastructure - see all reports for this category
Description: Following the bombing of the Consulate General in Istanbul in 2003 a fundamental security review identified Jakarta as one of the most vulnerable posts in the estate. The FCO decided in 2004 to move to a greenfield site, which we acquired in 2009 at a cost of £7.56m. Both staff and visitors are at significant risk in a country with a proven track record of terrorist attacks on western interests (including Embassies). In October 2010 HMT approved an earlier FCO investment decision to provide new offices at a cost of £29.5m. Mace (FCO Strategic Partner) were appointed in Dec 10 under a Works Instruction (target cost £22.63m) to deliver the new offices. Following a delay in the local permit process work started on site in June 11. Aim: to build safe and secure offices. Forecast proceeds of £11m in FY13/14 ( now anticipated 14/15) upon sale of current Embassy and Residence
DCA (RAG) Amber/Green
DCA text: Since last quarter, no change in RAG status, pending Gate 4 review before Full Business Case submission to HMT. Amber/Green rating due to need to improve benefits tracking.
Start date 2004-04-01
End date 2014-09-01
Schedule text Schedule completed
Baseline £5.64m
Forecast £2.44m
Variance -56.74%
Variance text: Underspend derived from coming in below the target cost which resulted in significant savings being realised at the end of the contract period
Whole Life Cost £29.45m
WLCost text: Budgeted costs remain as approved by MPA/HMT at full business case stage
Notes1:
Notes2:
Sourcefile IPA_2014.csv