2014 Report details for project: National Citizen Service
Project name | National Citizen Service - there are 3 reports for this project: 2013, 2014, 2015 |
---|---|
Google search | Google search on project name (opens in new window) ![]() |
Contracts | Contracts search (opens in new window) ![]() |
Organisation | CO (D2) - see all reports for this organisation |
Report year | 2014 (data is from September 2013) |
Category | Transformation - see all reports for this category |
Description: | National Citizen Service (NCS) is a flagship government programme that gives 16-year-olds the chance to learn new skills and get involved in their communities. NCS promotes: a more cohesive society by mixing participants of different backgrounds; a more responsible society by supporting young peoples transition into adulthood; and a more engaged society by enabling young people to work together to create social action projects in their local communities. NCS brings young people together from different backgrounds (e.g. religious, ethnic and socioeconomic) to work together, and teaches them what it means to be responsible and serve their communities. It is a high quality personal development programme that gives young people a chance to prove to themselves and their peers what they can do. NCS builds on a substantial range of government initiatives that aim to increase voluntary activity among young people and develop their life and citizenship skills. Such initiatives include the National Young Volunteers Service , the Millennium Volunteers programme, and Volunteering Together. NCS is also part of a broader agenda of improving services and outcomes for young people between the ages of 13-19, reflected in the Positive for Youth policy statement published in December 2011 as well as drawing inspiration from international programmes such as the Americacorps, a programme developed in the United States that supports volunteering and engagement in social action . |
DCA (RAG) | Amber |
DCA text: | NCS continues to be fully on track to achieve all of its outcomes following the novation of provider contracts to the NCS Trust in November. The successful delivery of the Autumn 2013 programme by the NCS Trust further adds to programme confidence. Risks remaining for the programme relate to HMT approval of the 15/16 programme budget, ERG approval of the 14/15 marketing spend and commissioning of contracts for 2015 in late April 2015 for signature on October 2015. |
Start date | 2011-10-01 |
End date | 2014-12-31 |
Schedule text | No departmental narrative |
Baseline | £104.85m |
Forecast | £104.85m |
Variance | 0.00% |
Variance text: | Variance occurred due to savings made on changes to programme model in 2013 as well as a reductions in funding to providers due to performance management measures and reduced PbR payments. |
Whole Life Cost | £325.40m |
WLCost text: | Whole life costs are reduced due to savings made in the 13/14 year, reduction in places to be delivered as well as more sophisticated payment mechanisms reducing costs. |
Notes1: | |
Notes2: | |
Sourcefile | IPA_2014.csv |