2013 Report details for project: Equitable Life Payment Scheme

Project name Equitable Life Payment Scheme - there are 3 reports for this project: 2013, 2014, 2015
Google search Google search on project name (opens in new window) opens in new window
Contracts Contracts search (opens in new window) opens in new window - under development
Organisation HMT (D15) - see all reports for this organisation
Report year 2013 (data is from September 2012)
Category Transformation - see all reports for this category
Description: The Scheme was established to makes payments to eligible Equitable Life policyholders for their Relative Loss as a consequence of regulatory failure.
DCA (RAG) Amber/Red
DCA text: The Scheme aims to distribute up to £1billion in the first 3 years, but anticipates undershooting this target as a result of not successfully tracing all policyholders. To mitigate against this the Scheme is implementing a publicity campaign to encourage people to come forward.
Start date 2010-05-01
End date 2014-04-01
Schedule text On schedule
Baseline £19.85m
Forecast £20.49m
Variance 3.23%
Variance text: Within tolerance.
Whole Life Cost £59.17m
WLCost text: The Scheme is broadly on budget with less than 3% overspend against the original, total outturn of £58m. HMT is working to identify potential opportunities for reducing the remaining operational costs, and has already identified c£500k cost reductions.
Notes1: £20,494,997 (as of 14th January 2013)
Notes2:
Sourcefile HMT_2013.csv