| Project name | London Programme for IT - there are 2 reports for this project: 2013, 2014 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | DOH (D12) - see all reports for this organisation |
| Report year | 2013 (data is from September 2012) |
| Category | ICT - see all reports for this category |
| Description: | LPfIT has overall responsibility for upgrading NHS information technology to make it possible for hospitals, community services and mental health trusts to implement Electronic Patient Record as per the LSP contract with BT. This will enable the NHS to provide better, safer care for patients wherever and whenever they need it. |
| DCA (RAG) | Amber/Red |
| DCA text: | OGC Gateway 5 Review forecast for December 2012. |
| Start date | 2003-12-18 |
| End date | 2015-10-19 |
| Schedule text | Programme is on schedule to end as per the current approved business case |
| Baseline | £163.35m |
| Forecast | £174.67m |
| Variance | 6.93% |
| Variance text: | Costs relate to the most recent approved CCN4 (2011) for LPfIT. Work is progressing on a revised case therefore there is a variance this quarter. |
| Whole Life Cost | £627.59m |
| WLCost text: | WLC is Gov Spend There is no Non Gov Spend in this business case |
| Notes1: | |
| Notes2: | |
| Sourcefile | DH_2013.csv |