2013 Report details for project: Mobile Infrastructure Project
| Project name | Mobile Infrastructure Project - there are 4 reports for this project: 2013, 2014, 2015, 2016 |
|---|---|
| Google search | Google search on project name (opens in new window) |
| Contracts | Contracts search (opens in new window) - under development |
| Organisation | DCMS (D5) - see all reports for this organisation |
| Report year | 2013 (data is from September 2012) |
| Category | Infrastructure - see all reports for this category |
| Description: | To facilitate the extension of mobile voice coverage to up to 60,000 premises and ten key roads where existing mobile coverage is poor or non-existent. |
| DCA (RAG) | Amber |
| DCA text: | As of 25/03/13 Project significantly de-risked by agreement between major Mobile Network Operators to share the infrastructure running costs. In final stage of procurement we fully expect to award contract to timetable. Will then agree rollout timescales with MIP provider. |
| Start date | 2011-10-03 |
| End date | 2015-03-31 |
| Schedule text | As of 25/03/13 State aid clearance gained 06/12/12. Agreements signed between major Mobile Network Operators in January. Invitation To Tender issued 31/01/13. Bids received 08/03/13. Contract award expected early May. |
| Baseline | £12.50m |
| Forecast | £4.50m |
| Variance | -64.00% |
| Variance text: | As of 25/03/13 The 12/13 budget is now £10m and the forecast is zero. Projected spend in 12/13 is less then originally forecast. The MIP was a highly complex proposal, needing the detailed agreement of the MNOs and Government to allow it to proceed. It took a little longer than we had hoped to reach a position which was acceptable to all. DCMS has agreed a budget re-profile with HMT which has brought the budget profile into line with forecast expenditure. |
| Whole Life Cost | £154.50m |
| WLCost text: | DCMS funding will cover the capital cost requirements to build the masts. Operating costs will be the responsibility of the supplier. |
| Notes1: | |
| Notes2: | |
| Sourcefile | DCMS_2013.csv |
Home Selection Search All Reports Projects +dates Projects +costs Organisations Years Categories